How Virginia Battery Permits Work
Virginia has the Uniform Statewide Building Code (USBC) adopted by the DHCD. All localities must enforce the USBC as a minimum standard. Virginia adopted the 2018 International Building Code and NEC 2017 (with 2024 amendment cycle moving to 2020 NEC). Every city and county requires permits for residential battery storage.
The Permit Process
Northern Virginia jurisdictions (Fairfax, Arlington, Loudoun) have online permit portals and typically process residential electrical permits in 7โ14 days. Richmond and Virginia Beach are similar. Dominion Energy's residential interconnection application portal is available online; standard residential storage review takes 3โ5 weeks.
Documents Required
Required: permit application, single-line diagram, UL 9540 spec sheets, Virginia DPOR-licensed electrical contractor info, and site plan. Virginia localities may require a Certificate of Occupancy update for systems with significant structural attachment.
- Permit application โ from your local building department
- Single-line electrical diagram โ your installer prepares this
- Equipment spec sheets with UL 9540 listing
- Licensed contractor license number
- Site plan โ battery location relative to panel